In the information center of Belarusian nuclear power plant, activities are continuing as part of the unified safety days, which take place in Belarus from February 20 to March 1, 2019. Читать далее

08:51 / 26.02.2019
574

Nuclear fuel will be delivered to Belarusian NPP site this summer, Deputy Energy Minister Mikhail Mikhadyuk told today before a board meeting of the Ministry of Energy, BelTA has learned.

Читать далее

10:07 / 12.02.2019
556

The decision of Geneva Meeting of the Parties of the Espoo Convention that  Belarusian side allegedly did not provide the public with “sufficient” information in support of the rationale for choosing Ostrovets site for the construction of  Belarusian NPP, has undermined the credibility of the Convention. This is stated in the comments on the website of the Ministry of Natural Resources and Environmental Protection of Belarus, BelTA informs. Читать далее

14:33 / 25.01.2019
1102

After the commission of the NPP, Belarus will reduce the share of gas in electricity production to 60%, Energy Minister Viktor Karankevich told today at the first National Forum on Sustainable Development in Minsk, BelTA has learned. Читать далее

08:57 / 23.12.2018
913

On December 22, 2018, in "Ostrovets" concert hall, a solemn meeting of the team of state enterprise "Belarusian NPP" took place, dedicated to the Power Engineers` Day. Читать далее

16:56 / 28.11.2018
1615

The assembly of supports for bearings and shells of the low-pressure cylinders of the turbine unit has begun in the machine hall of the second power-generating unit of the Belarusian nuclear power plant, the ASE Company press service told BelTA. The company is the general designer and general contractor for the project to build the Belarusian nuclear power plant. The company represents the engineering division of the Russian state nuclear industry corporation Rosatom. Читать далее

16:47 / 23.11.2018
1030

In the engine room of the power unit No. 2 of  Belarusian NPP, the installation of blocks for bearings and frameworks of low pressure cylinders (LPCs) of the turbine unit began, BelTA learned from the press service of the general designer and the general contractor of the construction - ASE (Rosatom Engineering Division). Читать далее

09:05 / 25.10.2018
5168

Vladimir Kravtsov, the chairman of the regional executive committee met with Yermukhamet Yertysbayev, the Extraordinary and Plenipotentiary Ambassador of the Republic of Kazakhstan to the Republic of Belarus. Читать далее

11:28 / 19.10.2018
3531

Belarus has established reliable mechanisms for emergency preparedness and response. This opinion was expressed by the Deputy Director General of the International Atomic Energy Agency (IAEA) Juan Carlos Lentijo on the results of the work of the agency’s mission in Belarus, BelTA has learned. Читать далее

11:45 / 28.09.2018
3246

Experts of Belarusian NPP during the visit to Rostov NPP have studied the experience of fueltranshipment, BelTA learned from Rosatom Eastern Europe.